(1) Challenge sustained. If the final resolution is that the proposed termination violates an existing collective bargaining agreement, the PBGC will dismiss the termination proceeding, all actions taken to effect the plan termination will be null and void, and the plan will be an ongoing plan. In this event, in a distress termination,
§ 4041.42(d) will apply as of the date of the dismissal by the PBGC.
(2) Termination sustained. If the final resolution is that the proposed termination does not violate an existing collective bargaining agreement and the plan administrator has notified the PBGC that the termination is to proceed, the PBGC will reactivate the termination proceeding by sending a written notice thereof to the plan administrator, and—
(i) The termination proceeding will continue from the point where it was suspended;
(ii) All actions taken to effect the termination before the suspension will be effective;
(iii) Any time periods that were suspended will resume running from the date of the PBGC's notice of the reactivation of the proceeding;
(iv) Any time periods that had fewer than 15 days remaining will be extended to the 15th day after the date of the PBGC's notice, or such later date as the PBGC may specify; and
(v) In a distress termination, the PBGC will proceed to issue a notice of inability to determine sufficiency or a distribution notice (or reactivate any such notice stayed under
paragraph (a)(3) of this section), either with or without first requesting updated information from the plan administrator pursuant to
§ 4041.45(c).