29 C.F.R. § 4204.11

Variance of the bond/escrow and sale-contract requirements.
eCFR amendment effective 2025-09-15 · current · last amended by 90 FR 39328, Aug. 15, 2025
Back to current
(a) General rule. A purchaser's bond or escrow under section 4204(a)(1)(B) of ERISA and the sale-contract provision under section 4204(a)(1)(C) are not required if the parties to the sale inform the plan in writing of their intention that the sale be covered by section 4204 of ERISA and demonstrate to the satisfaction of the plan that at least one of the criteria contained in § 4204.12 or § 4204.13(a) is satisfied.
(b) Requests after posting of bond or establishment of escrow. A request for a variance may be submitted at any time. If, after a purchaser has posted a bond or placed money in escrow pursuant to section 4204(a)(1)(B) of ERISA, the purchaser demonstrates to the satisfaction of the plan that the criterion in either § 4204.13 (a)(1) or (a)(2) is satisfied, then the bond shall be cancelled or the amount in escrow shall be refunded. For purposes of considering a request after the bond or escrow is in place, the words “the year preceding the date of the variance request” shall be substituted for “the date of determination” for the first mention of that term in both § 4204.13 (a)(1) and (a)(2). In addition, in determining the purchaser's average net income after taxes under § 4204.13(a)(1), for any year included in the average for which the net income figure does not reflect the interest expense incurred with respect to the sale, the purchaser's net income shall be reduced by the amount of interest paid with respect to the sale in the fiscal year following the date of determination.
(c) Information required. A request for a variance shall contain financial or other information that is sufficient to establish that one of the criteria in § 4204.12 or § 4204.13(a) is satisfied. A request on the basis of either § 4204.13 (a)(1) or (a)(2) shall also include a copy of the purchaser's audited (if available) or (if not) unaudited financial statements for the specified time period.
(d) Limited exemption during pendency of request. Provided that all of the information required to be submitted is submitted before the first day of the first plan year beginning after the sale, a plan may not, pending its decision on the variance, require a purchaser to post a bond or place an amount in escrow pursuant to section 4204(a)(1)(B). In the event a bond or escrow is not in place pursuant to the preceding sentence, and the plan determines that the request does not qualify for a variance, the purchaser shall comply with section 4204(a)(1)(B) within 30 days after the date on which it receives notice of the plan's decision.
(e) Method and date of issuance. The PBGC applies the rules in subpart B of part 4000 of this chapter to determine permissible methods of issuance under this subpart. The PBGC applies the rules in subpart C of part 4000 of this chapter to determine the date that an issuance under this subpart was provided.
Source credit, amendments & notes

[61 FR 34084, July 1, 1996, as amended at 68 FR 61355, Oct. 28, 2003; 90 FR 39328, Aug. 15, 2025]

29 C.F.R. § 4204.11 — Variance of the bond/escrow and sale-contract requirements. · eCFR amendment effective 2025-09-15 · https://pensionresource.website/EAMain?content=EAMain.Law&id=cfr29-4204.11&asof=2025-09-15 · printed Oct 16, 2026
On this page
  • (a) General rule.
  • (b) Requests after posting of bond or establishment of escrow.
  • (c) Information required.
  • (d) Limited exemption during pendency of request.
  • (e) Method and date of issuance.
Implements
Guidance addressing this section

No documents are primarily about this section.

Also cited in 2 other documents
PBGC
Final Rules
  • 90 FR 39320 Aug 15, 2025 — Miscellaneous Corrections, Clarifications, and Improvements
Proposed Rules
  • 90 FR 6894Proposed Jan 21, 2025 — Miscellaneous Corrections, Clarifications, and Improvements Comments due Mar 24, 2025

No court rulings in the library cite this provision yet.

No private letter rulings in the library cite this provision yet.

Each row is a version of the text as published by the official source. Code dates are the edition/release point that first reflected the change; regulation dates are eCFR effective dates. The library checks the official sources automatically, so new versions appear here on their own; “run” opens the sync that recorded a version.

EffectiveThroughSourceAmended by
Jul 1, 1997Jun 30, 2004CFR 2003 annual edition (revised as of 2003-07-01) run 127View
Jul 1, 2004Aug 14, 2025eCFR amendment effective 2025-09-15 run 290 FR 39328, Aug. 15, 2025View · Redline (sign in)
Aug 15, 2025Sep 14, 2025eCFR amendment effective 2025-08-15 run 2668 FR 61355, Oct. 28, 2003View · Redline (sign in)
Sep 15, 2025currenteCFR amendment effective 2025-09-15 run 2690 FR 39328, Aug. 15, 2025View · Redline (sign in)
Provision-level history (blame)